Green Line
0

Board approves Green Line builder

It’s official: Today the Fiscal and Management Control Board unanimously approved the recommendation to hire GLX Constructors to build the Green Line Extension! View the slides.

“Green Line extension contract officially approved” (Boston Globe)

“The award comes about two years after the board halted all progress on the project due to escalating costs that were projected to get as high as $3 billion. After the T made changes to the project’s station designs and the way the construction contract would be awarded, the agency now expects the total to costs $2.3 billion.”

Read More
Green Line
0

Green Line builder selected – and the Community Path will be fully built!

Great news: GLX Constructors (a joint venture of several engineering and construction firms: website) submitted the winning $1.08 billion bid for the GLX design-build contract, coming in below the price limit and including all six of the “additive options”! That means the project will include: 

  • Platform canopies
  • Additional elevators at select stations
  • Public art
  • A Community Path ramp to Chester Ave (by the cross Street Bridge)
  • Construction of the Community Path “missing link” from Washington St to the North Point/Lechmere area!
  • Enhanced MBTA maintenance facility

Thanks to all who have continued to fight for the Green Line and full Community Path! See some slides from the presentation.

Next steps: The contract must be approved by theFiscal and Management Control Board and MassDOT board before it is official.

Mayor Joe Curtatone’s statement: “This is a huge victory for Somerville, the region, and the Commonwealth. While there are still final steps to be taken before the apparent low bidder is officially chosen, we have a commitment that the Green Line will come to Somerville, and with it the full construction of the Community Path extension that our community has fought long and hard for. I want to thank Governor Baker, MassDOT, and the Fiscal Management Control Board for this well executed and thoughtful procurement process that incorporated input from more than fifteen years of a painstaking community process. Finally, thank you to all of our community activists for decades of work and action to make this project a reality.”

“MBTA names winning bidder for Green Line extension project” (Boston Globe)

“‘We could not have asked for a better outcome,’ said John Dalton, the project manager overseeing the rail expansion….GLX Constructors was chosen from two finalists. It had the lower of the two bids, but price was not the only factor: The winner was chosen based on who offered the best value while staying under an agency-mandated limit of $1.3 billion. The agency used a scorecard to rate the quality of the bids.”

“GLX constructors picked for Green Line design-build contract” (Cambridge Chronicle)

“With today’s price opening and the identification of the apparent successful design-build proposer for the GLX, we are truly on our way to making the Green Line Extension a reality for the people of Cambridge, Somerville and Medford,” said MBTA General Manager Luis Ramirez. “The selection process was extensive and thorough, and we are pleased that the outcome is that the cost is under our Affordability Limit.”

“MBTA chooses Texas’ contractor’s $1B bid for Green Line Extension” (Boston Herald)

“Great Green Line News – Senator Pat Jehlen” (Somerville Times)

Read More
Green Line
0

Join the Green Line construction working group

As part of a regional partnership with the Massachusetts Department of Transportation, and the Cities of Cambridge and Medford, the City of Somerville is seeking residents to serve on the Green Line Extension (GLX) Working Group. Major construction activities are expected to begin in early 2018, and the GLX Community Working Group will provide a collaborative forum for information exchange between the MBTA GLX Project Management Team and external stakeholders. The Working Group’s role will focus on community impacts from construction activities, and members will assist with planning and implementation of community meetings related to construction.

Each city will select one community representative per GLX station neighborhood, as well as two at-large members. Somerville has five GLX stations within its borders, and will therefore appoint five members in addition to the two at-large members for the Working Group. Representatives will be appointed for one-year, renewable terms.

Requirements & How to Apply:

The City of Somerville is seeking applicants with knowledge of or experience with GLX planning, community planning or advocacy, and/or construction management. Strong social networks in the neighborhood and multilingual capacity are important criteria for candidates. Interested individuals should submit a letter of intent by Friday, November 24, to transportation@somervillema.gov, or by mail to Transportation & Infrastructure Division, Somerville City Hall, 93 Highland Ave., Somerville, MA 02143.

Read More
Green Line
0

State Rep. Christine Barber on why the Green Line needs to go to Route 16

“Op-Ed: Build The Green Line Extension To Rt. 16” (Somerville Patch)

“The GLX stop at Route 16 not only brings public transportation access to a number of environmental justice communities, but would connect a greater region of car-centric suburbs to help provide an easy, accessible transit option for thousands of people in the Medford, Arlington, and Somerville area and beyond. This segment of the extension is, many transportation advocates would argue, one of the most beneficial to the Greater Boston area.”

Read More
Green Line
0

Environmental review of Green Line Extension to Mystic Valley Parkway

The Green Line to College Ave is happening, but the original plan was to extend at least to Mystic Valley Parkway, and planning continues on that potential extension. The MBTA has now released a preliminary environmental document for this separate project. On October 17, 2017, the MBTA filed a Notice of Project Change (NPC) with the Executive Office of Energy and Environmental Affairs (EEA). 

There will be a public meeting on this work on Nov 20.

EEA will now accept public comments on this document. Comments should be addressed to:

Secretary of Energy and Environmental Affairs
Executive Office of Energy and Environmental Affairs (EEA)
Attn: MEPA Office
EEA No. 13886
100 Cambridge Street, Suite 900
Boston MA  02114

Comments must be received by EEA no later than 5:00 PM on Tuesday, November 28.

Read More
Green Line
0

Green Line public meeting notes

Thanks to Ken Krause for the following notes from Monday’s meeting at Somerville High School…

OVERALL PROJECT OVERVIEW

+ Program Manager John Dalton reported that the process of selecting a contractor to complete the design and construction of GLX Phase I was nearing completion. (Phase I would extend the Green Line from a relocated Lechmere Station to College Avenue in Medford, with a separate spur extending from Lechmere to Union Square in Somerville. Phase II would further extend the Medford leg of the extension to Route 16 on the Medford/Somerville border.)

+ Three joint ventures bid on the Phase I “design-build” contract, and two of the bids have been certified as being within the “affordability limit” of the remaining project budget of $1.319 billion (the total budget, including money already spent and for 24 new Green Line cars, is $2.289 billion).

+ It will not be known until the bids are opened publicly on November 17 whether any of them include any of the six “additive options” that were cut from the original project; bidders were asked to try to fit as many of these as possible into their proposals while remaining within the budget. The additive options, which must be added in this order of priority determined by the MBTA, are 1) Platform canopies at each station; 2) Additional elevators at select stations; 3) Public art; 4) Additional connection to the Community Path at Chester Street in Somerville; 5) Extension of the Community Path between East Somerville and Lechmere Stations. 6) Enhanced Green Line vehicle maintenance facility in Somerville.

+ The MBTA plans to announce the selected design-build contractor and issue a Notice to Proceed on December 11, 2017. “Right now,” Dalton said, “we have everything in place that we need to get this project off the ground by then end of this year.” The Green Line extension is anticipated to be in operation four years later, in December 2021.

Read More
Green Line
0

Two firms say they can build the Green Line within budget

“Green Line extension back on track; cos. certify build within budget” (Boston Herald)

“Two companies have certified that they can design and build the Green Line extension to Somerville within the MBTA’s cost limit of $1.3 billion, allowing the long-anticipated project to advance to the next stage, officials said.”

Transportation Secretary Stephanie Pollack: “And while there’s lots more work to be done, I think that today really marks the day when we can be sure there’s going to be a Green Line extension.”

“T notes: Green Line ext. clears pricing hurdle” (CommonWealth Magazine)

“John Dalton, the project manager, declined to identify which bidders said they could do the work within the price limit and the one who said it couldn’t.  Three teams had been competing for the work under the names GLX Constructors, Green Line Partners, and Walsh Barletta Granite JV. All three submitted bids, but only two of them said they could do the work for less than $1.319 billion.”

Read More
Green Line
0

Green Line contractor bids coming in

“Bids for extending the Green Line are due Thursday” (Boston Globe)

“…the agency is asking the bidders to revive parts of the project that were unceremoniously dumped in 2016 in the face of a billion-dollar overrun, such as canopies over train stops, and the final 3,000-foot stretch of a bike and walking path to be built alongside the rails. As part of picking the contractor, the T said it will score bidders on their offers to restore up to six optional features that were previously eliminated – so long as they don’t push the value of the contract beyond the T’s maximum rate of $1.3 billion.”

Read More
Green Line
0

Federal money starts arriving for Green Line Extension

“Federal officials fork over cash for Green Line extension” (Boston Globe)

“The Green Line extension has been going on for a while, but the Commonwealth has been paying all the actual dollars for it,” said John Dalton, the MBTA manager overseeing the Green Line project. The payment, he said, is “comforting and reassuring, and underscores what we’ve been saying for a long time: that the FTA wants to see the project go forward.”

“Green Line Extension Gets First Federal Payment” (Somerville Patch)

“The state has spent about $536 million so far in its efforts to extend the Green Line into Somerville and Medford. Production was halted two years ago amid skyrocketing budget estimates, forcing a scaled-back design that is expected to cost $2.3 billion and add seven new stops in Somerville and Medford.”

“Federal money begins to flow into Mass. for Green Line Extension” (Metro)

“Dalton also told the board Monday that the project schedule is going to be moved up slightly to maximize the work that can be done during the 2018 construction season, though the completion date will not change. Dalton said he expects to give the design-build team the go-ahead, or notice to proceed, 61 days earlier than anticipated, on Dec. 11, 2017. The project completion date is still pegged at Dec. 10, 2021, Dalton said.”

Read More
About STEP
0

STEP at ArtBeat 2017!

Great to see everyone at ArtBeat! Thanks for dropping by the STEP booth and supporting the Green Line Extension and Community Path.

Read More
1 2 3 96