Green Line
0

The bridge closures are here

The price of the future Green Line through Somerville is a lot of annoying construction. In a couple of weeks that begins in earnest with the first major bridge closing. Here’s the schedule:

  • Broadway bridge at Ball Square: March 22, 2019 – March 2020
  • Washington St underpass in East Somerville: April 2019 – Fall 2019 and also Spring 2020 – Fall 2020
  • Medford St bridge at Gilman Square: July 2019 – Spring 2020
  • School St bridge: End of 2019 – Fall 2020
  • Cedar St bridge: Early 2020
  • Lowell St bridge: Summer 2020

The closures of the Broadway and Medford Street bridges are necessary in order to accommodate the construction of new Green Line light-rail tracks. Currently, these bridges are only wide enough to accommodate the existing commuter rail service that operates beneath them. The Washington St. bridge requires a complete reconstruction of abutments and structural span in order to accommodate the addition of new light-rail transit service and the Community Path.

“Here’s the schedule for the Green Line Extension bridge closures — and how to get around them” (Boston.com)

This article has useful maps for all three closures and their associated detours for vehicles, buses, bikes, and pedestrians.

Related Posts
Come to Green Line fundraiser!
Green Line FEIR accepted, Preliminary Engineering phase begins
Somerville Journal: Potential Green Line impact on businesses

Leave Your Comment

Your Comment*

Your Name*
Your Webpage