Somerville Journal: “State lays out timeline for Green Line project through Somerville”
Fall 2012: Start of reconstruction of the Medford Street railroad trestle near the Cambridge Line and the Howard Street trestle in Medford.
Summer 2013: Construction will begin on the new Lechmere, Union Square and Washington Street stations. Construction will also begin on the new maintenance facility in the Inner Belt.
2014: Construction will begin on the Gilman Square, Lowell Street, Ball Square and College Avenue stations.
2016: Construction of the new Lechmere, Union Square and Washington Street stations will be completed, with trolley service opening on that portion of the Green Line Extension.
2018: Construction will be completed of the remaining stops, except for Route 16.

Related Posts
Gov. Patrick’s transportation plan is good news for the Green Line extension
Boston Globe editorial in support of the Green Line Extension
Massachusetts to be sued for Green Line extension and other behind-schedule projects