Green Line updates from MassDOT

Some tidbits from the latest status report on MassDOT transit commitments:

  • Project cost is now estimated at $953.7 million.
  • The New Starts application is still in progress.
  • Preliminary Engineering will begin winter 2011.
  • The Green Line will open by Oct 2015, 10 months beyond the legal deadline. (MassDOT will propose an interim offset project that the public will be able to comment on.)

Download the report (PDF)